Project Location: California
0 OSHA recordable incidents

EBI’s Scope:

EBI mobilized its crew, equipment, and R3 mobile factory on an emergent basis to perform non-seg repairs, modifications and component fabrications at this geothermal facility after the plant experienced a transformer fire. EBI’s scope included:

  • Demolition and re-installation of the newly fabricated non-seg bus enclosure, covers and bus bars
  • Aligned and set new transformers
  • Fabricated and installed 22 new insulators
  • Silver plated all mating surfaces and painted new bus bars to prevent oxidation
  • Performed megger tests the bus on each unit to satisfactory results and installed new plant supplied braids
  • Installed new gasket material and applied silicone and bonded washers to prevent moisture intrusion
  • Primed and painted all new enclosures and covers

After successfully performing the scope of work, EBI cleaned their work area and demobilized all crew and equipment.