Project Location: Canada
0 OSHA recordable incidents
Project completed on schedule

Why EBI:

EBI was called to this Canadian power plant for refurbishment and realignment of the Isolated Phase Bus from the generator to the GSU.

Related Services

  • IPB Installation & Replacement
  • IPB Offline Inspection & Cleaning
  • IPB Repairs & Refurbishment
  • Replacement Parts & Fabrication
  • Silver Plating

Scope

  • Refurbish and realignment of the Isophase bus system from the generator to the GSU including the GSU LV bushing cabinets.
  • Furnish and install replacement IPB seal off bushings
  • Cryogenically clean the entire Isophase bus duct