At Victory Wind Project EBI wired 66ea 1.5 MW GE wind generators setting on 80 meter towers. These systems implemented the use of an aluminum bus down tower system versus cables. EBI also installed all the 35kv collection system splices, terminations, crossbondings, GSU transformers, Junction Boxes, along with all fiber optic splicing, terminations and testing.
|